How we time every alteration in our bridal studio (and what it taught us about pricing)

By Rachel, The Bridal Sewing Room · 6 min read

Ask a seamstress how long a lining hem takes and you'll usually get a confident answer. Ask her to prove it and things go quiet.

That was us too. For years we priced from memory. When we finally started writing down the real minutes for every step of every job, the surprise wasn't the everyday work. Our lining hems, for example, were priced about right.

The misses were the big custom jobs. A pair of sleeves built from scratch, or lace lifted and re-sewn by hand, took far longer than we'd ever guessed. Adding a lace underlay under a strapless bodice was the same story. We'd been quietly losing money on exactly the jobs we were proudest of.

Here's how we time work in our studio now and what the numbers showed us. At the end you'll find how to start timing your own jobs this week with a free stopwatch.

Why your hourly rate is only half the answer

If you've read how much to charge for alterations, you'll know how to work out an hourly rate that pays you properly. But a rate on its own doesn't price anything. A price is your rate multiplied by the time a job really takes.

Get the time wrong and a perfectly good rate still loses you money. If you charge for 30 minutes and the job takes 50, you've worked 20 minutes for free. Do that on every hem in wedding season and it adds up to weeks of unpaid sewing.

Most of us underestimate for an honest reason. We remember the sewing and forget the rest, like threading the machine or putting the dress back on the rack. Those minutes are real and they belong in the price.

How we started: paper slips

Our first system was a paper slip that went everywhere the dress went. Whoever picked up the dress wrote down their name beside the minutes for each step. At the end of every pay fortnight the slips were photographed and typed into one big spreadsheet.

It worked, and it gave us hundreds of timed steps across more than a hundred jobs. But paper has problems. Slips go missing, and somebody writes "hem 40" without saying whether that meant the lining or the tulle.

So we built a stopwatch that does the same job on a phone, and we've made it free for other seamstresses to use.

How we use the stopwatch in the studio

One studio code for the whole team. Everyone who sews for us opens the stopwatch on their own phone with the same studio code. That way every job shows up in one list, whoever worked on it. You invite people from inside the stopwatch, and only people with the code can see your jobs.

One job code per dress. When a dress comes in for its first fitting, it gets a job. The short job code goes on the dress ticket, so anyone who picks the dress up can find its timer in seconds.

Start when you pick it up, stop when you put it down. This is the habit that matters most. Press start before you thread the machine, not when the needle goes in. Press stop when the dress is back on the rack, not when the last stitch is done. If you only time the sewing, you'll end up with the same rosy numbers you had in your head.

Or give the prep its own timer. If starting the clock that early feels fiddly, add a prep step to the job instead. Time threading the machine and getting the dress out, then time putting it back on the rack. You'll be surprised how much those little minutes add up to across a week.

Time each step separately. A job is broken into stages: prep, cut, sew, press and finish. A hem isn't one number for us. It's the prep and the cut and the sew and so on, each with its own minutes. That's what lets you see where the time actually goes.

Write a note when something's different. Horsehair braid, lace edge, sequins, a train that has to come off and go back on. A short note beside the time is what makes the number useful later. "Hem, 2 layers, lace on top, 48 min" is gold. "Hem 48" is a guess waiting to happen.

Time the fittings too. The stopwatch lets you time each fitting as its own entry, from the first one through to pick-up. Fittings are a big part of bridal work, and if you don't know how long yours run, you can't build them into your prices. A fitting that runs 50 minutes instead of 20 is half an hour you'll never bill unless you know it's happening.

Your times live in the cloud, not on your phone. Every time you press stop, it's saved online against your studio. Drop your phone in the bath or swap to a new one, and nothing is lost. Open the stopwatch on the new phone with your studio code and every job is still there.

Install it like an app. You can add the stopwatch to your phone's home screen so it opens like any other app. The instructions come with the free download.

Download the times every fortnight. Every pay fortnight we download all the times as a spreadsheet and add them to our library of job times. It also gives us a quick check that the hours on the timers match the hours people were paid for.

What the numbers taught us

Here are a few things that came out of our own timing. These are real minutes from a working bridal studio, not targets.

Our everyday guesses were close. Our custom guesses weren't. Lining hems came out right where we'd always priced them. The big surprises were custom builds. Sleeves made from scratch and hand-sewn lace ran well past what we'd been charging for. Added underlays did too. If you only time one kind of job this month, make it your custom work.

Custom illusion sleeves and lace being fitted on a wedding gown
Before and after of a strapless satin gown with a long-sleeved lace underlay added
Before and after of a lace and crepe wedding gown with the lace reworked by hand and off-shoulder straps added

Some jobs are boringly consistent. Inserting new cups took 8 to 16 minutes across twelve dresses. Machine-sewn waist stays sat between 15 and 28 minutes across eleven. Once a job has that much steady data, we stop timing it every time and just spot-check now and then. That saves everyone a bit of fiddling.

Some jobs vary wildly, and that's the real lesson. Horsehair braid hems ran anywhere from 20 minutes to 3 hours, with the middle sitting around 80 minutes. The fabric and the number of layers drive it. If you charge one flat price for "horsehair hem", you'll lose on every big skirt. We now price those from the top of the range, or split them by layers.

A hem isn't a hem. A straight lining hem sat between 20 and 43 minutes. Two layers with a main fabric and a lining ranged from 47 to 110 minutes. If your price list only says "hem", those are very different jobs hiding under one line.

Bustles are easiest to price by the point. Once we started counting the points (we call them "bits"), bustles got predictable. A simple plastic loop point took about 3 to 5 minutes. A lace point took closer to 10. So a bustle with five simple points and a bustle with fourteen lace points are not the same job, even if a bride calls them both "a bustle".

Boning is a per-piece job. One bone sewn into a petersham casing by hand took 8 to 20 minutes. One sewn into sheer tulle took 20 to 33. Pricing boning "per dress" hides all of that.

One person's minutes aren't enough. Experienced sewists can take quite different times on the same step. That's why our benchmark times never come from one person on one good day. They're built from many jobs, done by several sewists over months, with one-off problems flagged and fixes left out. That way the number you see is what the job really takes in a working studio.

Rules we follow before changing a price

Timing data is powerful, so we're careful with it.

How to start timing your own jobs

You don't need a team or a spreadsheet to begin. Start with your next ten jobs.

  1. Open the stopwatch and set up your studio. Write your studio code somewhere safe.
  2. Give each dress a job code and put it on the ticket.
  3. Start the timer when you pick the dress up and stop it when it goes back on the rack.
  4. Add a short note whenever a job is a bit different from usual.
  5. After ten jobs, download your times and compare them with what you charged.

Most seamstresses find at least one job they've been undercharging for. That's usually the one you thought you knew best.

Free tools to help

The sewing job stopwatch is free. It runs on your phone and saves everything to the cloud, so your whole team can share one studio.

If you'd like a head start before you have your own numbers, the Time Guide has our studio's benchmark times for common bridal jobs, built the same careful way. When you're ready to turn your times into prices, the Price Sheet Builder multiplies your hourly rate by your real times for every job at once.

Not sure what your hourly rate should be? Start with the free Pricing Calculator. And when your prices are set, the Website Price List Maker turns them into a price guide you can paste straight onto your own website.

Tools built for seamstresses, not brides

Most alterations websites are written for brides. The Bridal Sewing Room is different. Everything we make is for seamstresses, to help you build a bridal business that pays you properly, and each tool is built and used inside a working bridal studio.

Follow The Bridal Sewing Room on Gumroad to hear when each new one comes out.

Price your work properly

Tools made inside a working bridal studio, from a free hourly rate calculator to a ready-made price sheet.

Browse the shop